Project
Black Building & Lock Room Rebuild
Description
Curry Construction demoed approximately 14,400 sq. ft. of the existing building. Formed and poured approximately 14,400 s.f. of 8” thick concrete floor slab with #4 rebar on 12” centers each way. Furnished and erected a 90’ by 160’ pre-engineered steel building. Installed a new roof-mounted Cambridge model S400 direct fired space heater in the new building.